Wright and Coombs – Construction Works Update

Aerial Construction

Take a drive along John Gorton Drive today to see the construction works in the northern parts of Wright and Coombs. The works are being completed north of Opperman Avenue in Wright and north of the existing suburb of Coombs.

Each suburb will contain open spaces, playgrounds, cycle networks and more, find out more about what makes Wright and Coombs so great!

Works are progressing as planned in each estate and are expected to be completed in the first quarter of 2019 once Operational Acceptance is achieved.  

Wright Works Update - June 2018

  • The earthworks for the project have now been completed.
  • Hydraulics have been progressing over recent months with the construction of sewer, stormwater and water mains well underway.
  • Construction of roads has also begun and the contractor is installing kerb and gutters.
  • Footpaths, verge landscaping, individual driveways (to verge only) and the open space areas will be the final component of works to be completed, work is expected to commence in the coming months.

Coombs Works Update – June 2018

  • The earthworks are largely complete with only a small section left for completion.
  • Hydraulics have been progressing well with sewer, stormwater and water mains well underway and due for completion in the coming months.
  • Construction of roads has begun in recent months and at this stage are progressing well.
  • Footpaths, verge landscaping, individual driveways (to verge only) and the open space areas will be the final component of works to be completed. Construction of the driveways recently commenced, with footpaths and landscape works to commence in the coming months.

What this means for Purchasers in the Northern Part of Wright and Coombs

Purchasers were advised of the estimated completion date range for construction works, this date range can be found on the front page of the Contract for Sale. After Operational Acceptance is achieved, the Suburban Land Agency will be in touch with purchasers to prepare for settlement. Interested in purchasing a block? View available land in the northern part of Wright.

 